User requirement specifications for process plant: what to include and how to write them
By Abhishek Bhatia, Managing Director
A user requirement specification (URS) is the owner's statement of what a plant, system or piece of equipment must do. It is written before design starts and in terms that can be tested. It fixes the operating envelope and the performance, safety and regulatory requirements that FEED, procurement and commissioning are later measured against. Each requirement should be measurable, carry a priority (shall, should or may) and trace to an acceptance test.
Most capital projects on an operating site start with a need that is clear to the people who run the plant and much less clear on paper. A user requirement specification is where that need is written down in a form that designers, vendors and commissioning engineers can all work to, and that the owner can hold them to at handover.
This article covers what a URS is, where it sits in the project lifecycle, what it should contain for process plant and equipment, and how to write requirements that can be verified. It applies whether the scope is a single skid, a utility upgrade or a new process area. It is written from the perspective of Integro Design Engineering Associates Ltd (IDEA), a process engineering and process safety consultancy in Glasgow that prepares and reviews URS documents for operating companies.
What is a user requirement specification?
A user requirement specification (URS) is the owner's document that defines what a plant, system or item of equipment must do, the conditions it must operate under and the standards it must meet. It describes the need and leaves the solution to the designer. The EU GMP guidelines on qualification and validation define it as the owner, user and engineering requirements needed for a feasible design.
The URS belongs to the operating company. It may be drafted with engineering support, but it should be reviewed and signed off by the people who will run, maintain and answer for the plant: operations, engineering, health and safety, and quality where product quality is at stake.
Two other documents are often confused with it. A functional specification describes how a proposed system will meet each requirement, and is usually written by the designer or supplier. A design specification sets out how the system will be built. Keeping the URS solution-neutral allows vendors to compete on how they meet the need. Where a specific solution is genuinely required, such as a site-standard instrument make or a material of construction, it belongs in the URS as a stated constraint with the reason recorded.
Where does a URS sit in a project?
A URS is drafted during feasibility and concept work, frozen before front end engineering design (FEED) or vendor enquiry, and then used as the reference for design reviews, factory and site acceptance tests and commissioning. Every later document should trace back to it. A requirement that cannot be found in the URS is difficult to hold anyone to at handover.
On projects run through front end loading stages (FEL 1 feasibility, FEL 2 concept, FEL 3 definition and FEED), the URS usually takes shape across FEL 1 and FEL 2. A feasibility study is decision-support in its own right, and the URS is often its most durable output: the written record of what the business decided it needs.
In medicinal product manufacture the URS has a formal role. Annex 15 of the EU GMP guidelines expects the specification for equipment, facilities, utilities or systems to be defined in a URS and/or functional specification, with the URS requirements verified during design qualification and confirmed at the vendor site before installation where applicable. Outside GMP the same logic holds, without the formal qualification stages.
Table 1. How the URS relates to the documents that follow it
| User requirement specification | Functional specification | Design specification | |
|---|---|---|---|
| Written by | Owner or user, often with engineering support | Designer or supplier | Designer or supplier |
| Answers | What is needed, and under what conditions | How the system will meet each requirement | How the system will be built |
| Typical timing | Feasibility and concept; frozen before FEED or enquiry | FEED or vendor bid | Detailed design |
| Verified at | Design review, FAT, SAT, commissioning (and design qualification in GMP) | FAT and SAT | Installation checks and as-built review |
FAT: factory acceptance test. SAT: site acceptance test.
What should a URS contain?
A URS for process plant normally contains an introduction and scope, a plain-language objective, the requirements grouped by category, the constraints and interfaces that limit the design, and supporting documents. The requirements section carries most of the value. For process plant it should cover the full operating envelope, including start-up, turndown, cleaning and abnormal conditions, and the design point.
Introduction and scope
The purpose of the document, the scope boundary (battery limits and tie-in points), definitions and acronyms, referenced standards and site procedures, and the revision status.
Objective
What the project is for and what problem it solves, written so that anyone approving the expenditure can follow it without technical background.
Requirements
Grouping requirements by category makes gaps easier to see. For process plant, the categories that most often matter are:
- Process and performance: throughput, product specification, yield and the operating envelope, including minimum turndown and future capacity.
- Operating modes: start-up, shutdown, cleaning in place (CIP), product changeover, and abnormal and emergency conditions.
- Safety and regulatory: the regimes the installation must satisfy, for example DSEAR 2002 where flammable materials are present, the Pressure Equipment (Safety) Regulations 2016 for equipment placed on the market and PUWER 1998 for work equipment. Include the process safety studies required, such as HAZOP to BS EN 61882:2016.
- Utilities and interfaces: steam, cooling water, compressed air and electrical supply, with the capacity and conditions available at each tie-in.
- Control, instrumentation and data: expectations for the control philosophy, integration with site systems, alarms and data recording.
- Materials, hygiene and environment: materials of construction, surface finish where product quality depends on it, and emission and effluent limits.
- Maintenance and lifecycle: access, spares, site-standard equipment, design life and the documentation required at handover.
Supporting documents
Process flow diagrams, site layout, existing P&IDs (piping and instrumentation diagrams), site engineering standards and, where operator interaction is itself a requirement, a mock-up of the operator screen.
How do you write a requirement that can be verified?
Write each requirement as a single statement with a unique reference, a measurable value and tolerance, and the test that will prove it. Use "shall" for mandatory requirements, "should" for recommendations and "may" for permitted options, following the ISO convention for verbal forms. Words such as "improve", "adequate" or "sufficient" cannot be tested and leave the requirement open to interpretation.
Four habits make the difference:
- One requirement per statement. A sentence containing "and" often hides two requirements, one of which gets missed at testing.
- A unique reference (for example REQ-PR-01), so that design documents, test protocols and change requests can point to it.
- A value, a tolerance and a condition. State the units precisely, including gauge or absolute pressure, and the operating case the value applies to.
- An acceptance criterion. If no one can say how a requirement will be tested, it is not ready to issue.
Reserve "will" for statements of fact, such as a utility the site will provide, so that it is not read as an obligation on the supplier. "Can" describes capability only.
Table 2. From weak statements to verifiable requirements
| Weak statement | Verifiable requirement |
|---|---|
| The system will improve bottling throughput. | REQ-PR-01: The spirit supply system shall support a filling line rate of 450 bottles per minute at the design product and filling conditions stated in the URS. Verified at SAT by a timed production run. |
| System A can achieve 99.9% purity. | REQ-PR-02: Product leaving the system shall have a purity of not less than 99.9% by mass at all feed rates between minimum turndown and design rate. Verified by the analytical method named in the URS during performance testing. |
| The system must handle feed rates from 100 to 1,000 litres per hour. | REQ-PR-03: The system shall operate stably and meet REQ-PR-02 at any feed rate between 100 and 1,000 L/h. Verified at commissioning by step changes across the range. |
| Pressure shall be regulated between 1 and 10 bar with ±0.1 bar accuracy. | REQ-CI-04: Pressure at the measurement point shown on the P&ID shall be controllable at any set point from 1 to 10 barg and held within ±0.1 bar of set point in steady operation. Verified at SAT. |
| Cleaning shall be sufficient. | REQ-HY-01: All product-contact surfaces shall be cleanable in place without dismantling. Verified by visual inspection and swab testing after a full CIP cycle. |
The 450 bottles per minute figure is the target throughput from a distillery bottling line spirit supply upgrade delivered by IDEA.
Where URS documents usually go wrong
The weaknesses that cause trouble later are usually visible in the draft, if someone reads it with acceptance testing in mind.
- The draft names a solution. "A plate heat exchanger" narrows the options. "Cool the product from X °C to Y °C at design rate" lets the designer choose, and leaves design responsibility where it belongs.
- Only the design point is defined. Turndown, seasonal variation, product changeover and future capacity are where plant most often falls short of expectations.
- Utilities are assumed. The steam, cooling or electrical capacity available at the tie-in was never confirmed.
- Departments disagree inside the document. Production, quality and maintenance requirements conflict and no one has resolved which takes precedence.
- The URS changes informally after issue. Changes agreed in meetings never reach the document, so the reference used at handover is out of date. Changes after issue should go through the same management of change process as the plant itself.
What a well-written URS protects
A URS gives every party the same reference from the first estimate to the final handover. Cost and programme estimates are made against defined requirements. Risks such as a missing operating mode or an unconfirmed utility are found while they are still cheap to address. At handover, acceptance becomes a matter of testing against agreed criteria, which removes most of the room for dispute.
Commissioning is where an unclear URS is most often discovered, and it is the most expensive point at which to discover it. The same discipline applies across sectors, from distilled spirits to chemicals and pharmaceuticals, and to small modifications as much as new plant.
Using a URS on your next project
The effort that goes into a URS is small compared with the cost of the decisions it informs. It is most effective when it is written early, owned by the operating company, reviewed by everyone who will live with the plant and kept under change control until handover.
IDEA prepares and reviews user requirement specifications as part of its process engineering and plant design services, usually alongside feasibility and concept work and before FEED. If you are preparing a URS for a new process area or a significant modification, IDEA's process engineering team can review a draft or help you write one.
Frequently Asked Questions
The operating company owns the URS, even where an engineering consultancy drafts it. Operations, maintenance, health and safety, and quality should all review it before issue. A URS written by a vendor tends to describe the vendor's product, which defeats its purpose.
The URS states what is needed and under what conditions. The functional specification, usually written by the designer or supplier, explains how the proposed system will meet each requirement. Each functional statement should reference the URS requirement it answers.
In medicinal product manufacture, in practice yes. Annex 15 of the EU GMP guidelines expects the specification for equipment, facilities, utilities and systems to be defined in a URS and/or functional specification, and the MHRA’s GMP guidance points UK manufacturers to the same guide. Outside GMP, no UK regulation requires a document with that title. Related duties still apply: under CDM 2015 the client must give designers and contractors pre-construction information, and recorded requirements make it easier to show that equipment is suitable for its intended use under PUWER 1998 and that explosive atmospheres were considered at the design stage under DSEAR 2002.
They are different documents. A safety requirements specification under IEC 61511 defines the safety instrumented functions and their integrity requirements, and is developed after the hazard and risk assessment. A URS can require that any safety instrumented system is designed to IEC 61511, but it does not replace the safety requirements specification. IDEA's functional safety assessment and design work covers that stage.