Practical Elements of Commissioning

By Michael Oates, Senior Process Engineer

Commissioning is always a hectic period of a project lifecycle.

There are many moving parts and parties to coordinate, where long, tiring days often become the norm to meet project timelines. It is also normally one of the most dangerous stages of a complete plant lifecycle, so good planning, controls and procedures are a necessity to ensure that commissioning is completed in a safe and timely manner.

Whilst there are many steps, procedures and protocols to consider, this article aims to highlight some of the more important.

These tools can be split into two types of categories:

  1. Documents and tools that should be prepared, approved and made available before commissioning.
  2. Activities conducted during commissioning.

Prior to starting commissioning, the following documents and tools should be considered.

Commissioning Plan:

This plan should detail day-to-day activities to be scheduled across the commissioning timeline. The plan must be realistic and consider engineering staffing plans, key dates for utility availability (power, compressed air, water and so on), and be used to highlight any potential ‘pinch-points’ within the commissioning timeline.

The plan should also outline commissioning nodes. These help to split the plant down into more manageable areas – but also clarify which areas should be commissioned first in order to allow commissioning of other areas (e.g., utility nodes).

Commissioning Organisation Chart:

Clearly defines who has overall responsibility at various stages of commissioning including:

  • Plant Erection & Construction.
  • Commissioning (pre-commissioning, cold and hot commissioning).
  • Performance trials (takeover / handover).

Deviation and Concession Procedures:

Protocols should be in place so that any member of the commissioning team can raise a deviation or concession at any time. All members of the commissioning team should be aware of the differences between the two:

  • Deviations refer to changes arising that either have the potential to prolong the commissioning programme or where the solution to resolve the issue costs greater than any pre-agreed commissioning overhead costs.
  • Concessions refer to changes arising that do not have an impact on overall commissioning or can be resolved by commissioning overhead costs.

Other required documents include RAMS for each commissioning stage / procedure, however that would require a whole discussion in their own right.

Once commissioning begins, the following tools and activities should be considered. Planning to include for these items should be conducted ahead of commissioning so that engineers and contractors alike are aware of their expectations during the commissioning process.

Punch lists:

These are vital for recording and categorising snags. A well-prepared and managed punch list can significantly reduce commissioning time and helps identify key snags that could hinder commissioning progress. The punchlist should include:

  • Snag Categories. These categories should cover all applicable commissioning stages from construction all the way through to plant takeover / handover.

Some examples include:

1. An automatic valve with no compressed air supply – this should be resolved before ‘dry-testing’ that valve.

2. A flow transmitter with inconsistent readings – this should be resolved before handover.

  • Responsible Person / Party: This should indicate who shall be responsible for closure of the punch list item.
  • Target date for punch list closeout to ensure commissioning remains on track.

Lock Out-Tag Out (LOTO) Equipment:

As well as ensuring all members of the commissioning team are LOTO-trained, the principal contractor / commissioning team must have access to:

  • Lock boards complete with padlocks, HASPS and tagout labels.
  • Lockbox including master key(s).
  • Alternative lockout devices including gate valve lockouts and chains.
  • LOTO book.

Daily Meetings between all key commissioning personnel are essential. This should include representatives from all parties and include key stakeholders (where applicable and appropriate) and be led by the lead commissioning engineer. Daily meetings should cover:

  • The previous day’s activities and progress, highlighting any areas of success and any causes of concerns.
  • Health & Safety matters.
  • Discuss the commissioning activities planned for the day ensuring:
  1. All parties are aware of the active commissioning areas.
  2. There is sufficient resource available for each of the planned commissioning activities to be carried out in a safe and controlled manner.
  3. Any activities being carried out simultaneously by separate groups or contractors are reviewed ensuring that any extra measures (such as additional plant isolations) are accounted for and implemented.
  • Look ahead to the planned commissioning activities for the next 2-3 days, ensuring that key requirements for future progress are planned and are progressing on schedule.

CONTACT US

Let’s Discuss Your Requirements

At Integro Design Engineering Associates (IDEA) Ltd. , we can help guide you through the commissioning process by providing clear and concise protocol and planning documents tailored specifically to your plant and your own organisational procedures. We can also provide guidance on specific commissioning processes and steps from our diverse engineering team who have experience across a wide range of sectors and even provide our own engineers to offer support if you have limited resource available.