Management of change (MoC) in process safety: a practical guide for high hazard sites

By Zac Meadows, Operations Director

Management of change (MoC) is the part of a process safety management system that makes sure changes to plant, processes, procedures and organisation are assessed before they are put in place. Anything that is not genuinely like for like needs assessment, scaled to the hazard. Organisational changes count too, as the Texas City and Hickson & Welch incidents showed. MoC works when triggers are clear, actions are closed out and performance is measured.

Changes happen on high hazard sites every week. A valve is replaced with a different model, a trip setpoint is adjusted, an inspection is deferred, a supplier substitutes a component, or a team is restructured. Each change can look minor on its own. The risk usually sits in the knock-on effects: a safeguard that is now less reliable, a hazard that was not there before, or a workload that no longer leaves time for the checks the safety case assumes.

This article explains what management of change requires, where it sits in a process safety management system, what the Texas City investigation found about organisational change, how to decide what counts as a change, how to scale the process to the hazard, and which indicators show whether it is working.

What is management of change in process safety?

Management of change (MoC) is the procedure a site uses to identify, assess, approve, implement and close out changes to plant, processes, procedures and organisation before they affect the control of major accident hazards. For COMAH establishments, it is one of the matters a safety management system must address under Schedule 2 of the COMAH Regulations 2015.

A change can affect process safety in three ways. It can make an existing barrier less reliable, for example when a proof test interval is extended. It can introduce a new hazard, such as a different cleaning chemical. Or it can raise the level of risk, through higher throughput, a higher operating temperature or a heavier operator workload.

People are good at seeing the direct effect of a change and less good at seeing second order effects, particularly under time pressure. MoC exists to ask one question in a structured way: what else does this change affect, and is the risk controlled before it goes live? The form records the answer. The barrier is the review that produces it.

What did Texas City teach the industry about organisational change?

The US Chemical Safety Board (CSB) found that poorly managed mergers, organisational changes and budget cuts increased the risk of catastrophe at BP's Texas City refinery, where 15 workers died in 2005. It recommended that MoC reviews should cover organisational, personnel and policy changes. HSE guidance for UK major hazard sites sets out the same expectation.

The CSB's recommendation to OSHA noted that the US Process Safety Management standard required MoC for changes to process chemicals, technology, equipment, procedures and facilities, but did not explicitly require it for organisational, personnel and policy changes. It cited a 2002 survey in which only 44% of chemical processing companies assessed organisational change within their MoC programmes.

The investigation also found failures in the MoC that did exist. According to the CSB chair's testimony to Congress in 2007, the explosion killed 15 workers and injured 180. Design and equipment changes had not been evaluated under BP's MoC policy even where the equipment was designated safety critical, and operators and supervisors had been allowed to alter procedural steps without an MoC review. Where an MoC was carried out for the placement of a trailer, hazard review actions were not closed and the change did not receive final approval. Budget pressure had also cut training positions by nearly 75%, and the closure rate for process safety management actions at the site had fallen to 79% by 2004.

The UK has its own example. HSE's information sheet Organisational change and major accident hazards (CHIS7) describes the 1992 fire at Hickson & Welch in Castleford, which killed five employees during the cleaning of a vessel. Following a reorganisation, the task had been organised by inexperienced team leaders reporting to an overworked area manager. HSE observes that organisational changes are often not analysed and controlled as thoroughly as plant changes, and lists examples that should be assessed, including delayering, outsourcing, downsizing, multi-skilling and changes to key personnel. CHIS7 was published in 2003 and refers to the earlier COMAH Regulations, but its framework of getting organised, assessing risk, and implementing and monitoring the change remains a practical starting point.

What counts as a change, and what is genuinely like for like?

Any change that is not genuinely like for like needs assessment. Like for like means the replacement matches the original in material, rating, performance, control behaviour, hazardous area suitability and inspection requirements. If any of these differ, or the change alters procedures, operating limits, staffing or competence, it should enter the MoC process.

"Like for like" is a narrower test than "same size and fits the flange". The table below sets out the attributes a replacement must match before it can bypass MoC.

Table 1. The like for like test

Attribute What must match Example that fails the test
Material specification Same grade, with the same compatibility with the process fluid A supplier offers an alternative gasket material
Pressure and temperature rating Same rating, or documented equivalence for the design case A lower rated valve body that fits the existing flanges
Performance Same duty: pump curve, valve capacity, relief capacity A replacement pump with a different curve changes downstream pressure
Control philosophy and fail position Same control response and fail-safe action A fail-closed actuator replaced with a fail-open one
Hazardous area compliance Equipment group, category and temperature class suitable for the zone A replacement motor without suitable ATEX marking for the area
Inspection, testing and maintenance Same regime and proof test requirements A new instrument that needs a different proof test procedure

Beyond equipment, MoC should catch everyday changes such as new operating limits or setpoints, altered alarm or trip settings, revised start-up or shutdown sequences, modified cleaning regimes, deferred inspections, and changes of supplier for critical spares.

Temporary changes need particular attention. A bypass fitted "until the new part arrives" can stay in place for months, and the site becomes used to operating with a weakened barrier. Every temporary change should have an expiry date, a review interval and clear criteria for extension or removal.

Organisational changes belong in scope as well. A simple set of trigger questions helps people decide without guessing:

  • Is it like for like in specification, performance and duty?
  • Does it affect operating limits, alarms, trips or procedures?
  • Does it affect inspection, testing or maintenance?
  • Does it affect hazardous area compliance or relief protection?
  • Does it affect staffing, competence or supervision?

A yes to any question means an MoC should be raised.

Making MoC proportionate and hard to bypass

An MoC process that applies the same depth of review to every change becomes slow, and a slow process gets bypassed. COMAH Schedule 2 requires the safety management system to be proportionate, and HSE's CHIS7 recommends categorising changes, with a higher level of management approval for more safety-significant categories. Table 2 shows one way to structure this. Each site should set its own criteria against its own risk matrix.

Table 2. Scaling MoC to the change (illustrative)

Category Typical characteristics Review route Approval
Minor Like for like confirmed; low consequence; no effect on safeguards Originator plus a competent checker Area or line manager
Moderate Technical differences; possible effect on a safeguard or procedure Discipline review (process, mechanical, EC&I, operations) plus process safety review Engineering or operations manager
Major Affects major accident scenarios, operating limits, safeguards or safety report assumptions Formal hazard study, such as HAZID or HAZOP; process safety sign-off; pre-start-up safety review Senior manager accountable for accepting the residual risk

Clear roles make the process faster. The originator explains the change and the reason for it. Discipline reviewers check the technical effect. A process safety reviewer checks the effect on safeguards, the hazard assessment and the actions. The approver has the authority to accept the residual risk.

Four failure patterns appear repeatedly:

  • Paper MoC. The procedure exists but is raised after the change, or not at all, because it feels like administration. Simpler forms, clear triggers and leaders who welcome early escalation do more than additional paperwork.
  • Approval after the event. If changes are implemented and then approved, MoC has become a record rather than a barrier. This usually means the process is too slow for low risk changes.
  • A weak link to mechanical integrity. If inspection intervals can be extended or work deferred without a process safety review, the condition of safeguards can decline unnoticed. This matters most on ageing process plant, which COMAH Schedule 2 names specifically.
  • Changes driven by contractors and suppliers. Substitutions offered to protect a programme can be entirely reasonable, provided they go through the same assessment.

Cumulative change is a further risk on expanding sites, where several projects each pass their own review but nobody looks at how they interact. On one food and drink manufacturing site, a site-wide HAZID structured to support Management of Change considered process hazards, traffic movements and adjacent operations together, giving management one consolidated view of major risks as the site grew.

Which KPIs show whether MoC is working?

Useful MoC indicators are mostly leading: overdue MoC actions, temporary changes past their review date, time from raising to approval by category, and the share of MoCs with a documented review of the effect on safeguards. Lagging indicators, such as incidents where change contributed, confirm what the leading set should have predicted. COMAH Schedule 2 allows safety performance indicators within monitoring.

Leading indicators worth tracking include:

  • number and age of overdue MoC actions
  • percentage of temporary changes past their review date
  • average time from MoC raised to approval, by category
  • percentage of MoCs with a documented review of the effect on safeguards
  • changes found by audit that never entered the MoC process
  • number of emergency changes, and their causes

Lagging indicators include incidents and near misses where an unmanaged change contributed, audit findings on MoC compliance, and equipment failures linked to altered maintenance regimes.

For organisational change, CHIS7 recommends choosing indicators specific to the risks identified, measuring before implementation so there is a baseline, and favouring lead measures such as overtime levels and maintenance backlogs. Texas City shows why closure matters: the CSB testimony records that the closure rate for actions from process safety incident investigations at the site was 33%.

For a structured check of the whole process, the IChemE Safety Centre's Management of Change guidance, published in December 2025, sets out commonly experienced MoC issues and troubleshooting recommendations, with self-assessment, audit and troubleshooting checklists.

An indicator earns its place only if a worsening trend triggers a management discussion and a corrective plan. Tracking overdue actions without resourcing their closure adds a figure to a report and changes nothing on site.

What this means in practice, and how IDEA can help

Effective MoC comes down to a few habits: treat anything that is not genuinely like for like as a change, include temporary and organisational changes, scale the review to the hazard, close actions before the change goes live, and measure whether the system is doing its job.

IDEA supports duty holders with MoC as part of wider process safety management. This includes MoC procedures with clear triggers and decision trees, proportionate assessment routes, templates focused on the effect on safeguards, and training for operators, supervisors and engineering teams. We also carry out MoC health checks within an independent process safety management audit, help sites recover backlogs of overdue actions, set up MoC performance indicators, and deliver the hazard studies that major changes need, as in our process safety support for a major site change at a distilled spirits site.

If you are reviewing your MoC arrangements or planning a significant change, contact our process safety team to discuss a proportionate review for your site.

Frequently Asked Questions

MoC is the management system that controls how changes are proposed, reviewed, approved, implemented and verified. Risk assessment is one step within it, used to evaluate the hazards and the effect on safeguards of a specific change.

Yes. Temporary changes should be raised, tracked and reviewed in the same way as permanent ones. Each should have an expiry date and clear rules for extension or removal, so that a temporary measure does not become permanent by default.

A replacement is like for like when it matches the original in material, rating, performance, control and fail-safe behaviour, hazardous area suitability and inspection requirements. If any of these differ, the replacement is a change and should be assessed.

They should be assessed for their effect on major hazard control. HSE's information sheet CHIS7 gives guidance on doing this, covering changes such as restructuring, downsizing, outsourcing and changes to key personnel. The Texas City and Hickson & Welch investigations both identified poorly managed organisational change as a contributing factor.

Useful leading indicators include overdue MoC actions, temporary changes past their review date, time to approval by change category, and the percentage of MoCs with a documented review of the effect on safeguards. Each should trigger action when it worsens.