How to demonstrate ALARP: a practical method from HAZOP action to defensible decision
A seven-stage method for defining the hazard, developing risk-reduction options and documenting a defensible decision.
By Ross Kohler, Senior Process Safety Engineer
Demonstrating ALARP (as low as reasonably practicable) means showing that every further risk reduction measure has either been implemented or rejected because its sacrifice would be grossly disproportionate to the safety benefit. In practice, relevant good practice is applied first, credible options are compared against the current position, and formal cost benefit analysis is reserved for decisions where the answer is not clear. The decision record, approved by whoever owns the residual risk, is what makes the conclusion defensible.
A HAZOP (hazard and operability study) or LOPA (layer of protection analysis) rarely ends with a clean list of things to do. It ends with actions. Some are plainly required, some depend on assumptions that need testing, and some would cost a great deal for a benefit that is hard to put a number on. Each one eventually needs a decision, and for a duty holder each decision has to stand up to the regulator, to insurers and to the people who will operate the plant.
This article sets out a practical ALARP assessment methodology for reaching those decisions under UK law. It covers the legal basis, how to judge how much analysis a decision needs, what counts as sacrifice in a cost comparison, how gross disproportion is judged, and what a defensible decision record contains. It draws on Health and Safety Executive (HSE) guidance and on process safety studies delivered by Integro Design Engineering Associates Ltd (IDEA).
What does demonstrating ALARP actually require?
Demonstrating ALARP means showing that further risk reduction measures have been implemented unless the sacrifice in money, time or trouble would be grossly disproportionate to the risk reduction gained. The test comes from Edwards v National Coal Board (1949). HSE applies the same test to duties expressed as “so far as is reasonably practicable” (SFAIRP) and to the general duty under the Control of Major Accident Hazards Regulations 2015 (COMAH).
The legal anchor for major hazard sites is regulation 5 of the Control of Major Accident Hazards Regulations 2015 (SI 2015/483), which requires every operator to take all measures necessary to prevent major accidents and limit their consequences for human health and the environment, and to demonstrate that it has done so. HSE’s principles for judging whether risk has been reduced ALARP treat that duty as equivalent to reducing major accident risk ALARP.
Three features of the test shape everything that follows.
- It is weighted towards safety. HSE’s ALARP “at a glance” guidance is explicit that the presumption is to implement the measure. This is not a balance of costs and benefits; a measure is adopted unless its sacrifice is grossly disproportionate.
- Rigour scales with risk. The greater the initial risk, the more rigorous the argument that it has been reduced ALARP needs to be. Low risks do not need elaborate analysis.
- It is not zero risk, and not every conceivable barrier. HSE lists both as fallacies. ALARP accepts that residual risk remains, and it does not require barrier after barrier where each one adds little.
The judgement belongs to the duty holder. Engineers and consultants inform it, but the decision to accept a residual risk is a leadership decision and should be recorded as one.
A note on currency: HSE has stated that it is reviewing its ALARP guidelines for inspectors, first published in 2001 with minor updates in 2003, while confirming no intent to change the principles of its tolerability framework. This article reflects the guidance published at the date above and will be revised when HSE publishes its update.
When is relevant good practice enough, and when do you need a formal assessment?
Most ALARP decisions are settled by relevant good practice: recognised standards, approved codes of practice and HSE guidance that already represent a judgement of what is reasonably practicable. A formal assessment, sometimes including cost benefit analysis (CBA), is needed where good practice does not cover the risk, where several credible options exist, or where a measure is proposed for rejection.
HSE’s guidance describes comparison with relevant good practice as the way most situations are decided. Where a situation is complex or novel, good practice is followed as far as it goes and the remaining question is decided from first principles. Even then, many first-principles comparisons are qualitative: if a measure is cheap and the risk reduction significant, it is required without further analysis.
Two limits apply. A universal practice in an industry is not necessarily good practice. And a CBA cannot be used to argue against relevant good practice, against a statutory duty, or to justify a risk that is intolerable. Cost comparison is a tool for the residual questions, not a route around the obvious ones.
The table below is the routing IDEA uses when a HAZOP or LOPA produces a set of actions. Its purpose is to put detailed effort where the decision is genuinely difficult and to let straightforward actions progress.
Table 1. Routing HAZOP and LOPA actions to the right depth of ALARP assessment
| Action type | Route | Depth of analysis | Evidence for the record |
|---|---|---|---|
| Measure required by law or relevant good practice | Implement | Confirm the good practice is relevant and correctly applied | Reference to the standard or guidance; implementation record |
| Risk intolerable against the site’s risk criteria | Implement, or change the operation | Not a matter for cost comparison | Risk basis; action, owner and date |
| Scenario, frequency or safeguards uncertain | Further risk assessment before deciding | LOPA, consequence assessment or human reliability review | Revised risk basis with stated assumptions |
| Several technically credible measures | Structured optioneering | Multidisciplinary comparison of effectiveness, feasibility and cost | Options register and selection rationale |
| Measure costly, difficult, or proposed for rejection | Formal ALARP justification | Comparison against the present situation, gross disproportion and sensitivity analysis | CBA, sensitivity results, approval by the risk owner |
A seven-stage method from hazardous scenario to approved decision
1. Define the credible hazardous scenario
State the initiating event, the consequence pathway, the people exposed and the safeguards claimed. Scenarios usually come from a HAZOP carried out to BS EN 61882:2016 or from a HAZID (hazard identification study). Avoid scenarios that combine unrelated causes or outcomes, and write down the assumptions and boundaries, because the rest of the assessment inherits them.
2. Establish the current risk and safeguards
Confirm which safeguards genuinely apply to this scenario, their condition, and any dependence between them. LOPA gives a consistent view of independent protection layers and residual risk where the severity justifies it. Treat numerical precision with care: a frequency carried to two significant figures on the back of generic assumptions is not more defensible than a well-argued order of magnitude.
3. Identify further risk reduction options
Start with inherently safer options (elimination, inventory reduction, substitution, moderation of conditions) before engineered protection, and engineered protection before procedural controls. HSE also expects options to be considered both across the whole system and location by location: a measure ruled out site-wide on cost may still be reasonably practicable at the highest-risk locations.
Credible options can include process changes, inventory reduction, layout and segregation, containment, relief, mechanical integrity improvements, detection and alarms, interlocks and safety instrumented functions, operating changes and emergency mitigation. Multidisciplinary optioneering helps avoid defaulting to the first recommendation made in the workshop.
4. Assess technical and operational feasibility
Feasibility at this stage is decision support, not a formality. Consider integration with existing plant, space, operability, maintainability, inspection and proof testing, human factors, hazardous area implications, tie-ins, shutdown requirements and the risks introduced by construction itself. For a retrofit, the risk of installing the measure has to be weighed against the benefit it provides once installed. Temporary operating arrangements during implementation need the same scrutiny, and the safeguard has to stay effective through design, installation, operation and maintenance.
5. Determine the sacrifice
Cost each option on the basis described in the next section. The sacrifice is what the duty holder gives up to implement the measure, not the full capital value of a wider project. Depending on the option, it may include engineering, procurement, installation, civil and structural work, electrical and control changes, shutdown, maintenance, inspection, testing, training and lifecycle operating costs.
Early estimates can use an expenditure range to screen alternatives and reveal lower-sacrifice routes to similar risk reduction. Greater precision is worth the effort where it could change the decision.
6. Make the ALARP judgement
Compare each option against the present situation, not against each other alone. HSE’s position is that the option, or combination of options, that achieves the lowest residual risk should be implemented provided its cost is not grossly disproportionate. A less protective but significantly cheaper option cannot be preferred on cost grounds. For existing plant, the outcome may legitimately be a higher residual risk than a new plant would achieve, because retrofitting costs more and carries its own risks; that reasoning should be stated, not assumed.
7. Document and approve the conclusion
Record the decision in a form that someone who was not in the room can follow and challenge. Approval should sit with someone who has the technical authority and who owns the residual risk. The contents of a defensible record are set out in the closing section.
What counts as sacrifice in an ALARP cost comparison?
Sacrifice is the non-recoverable cost to the duty holder of implementing the measure: installation, operation, maintenance, training and any productivity loss it causes. Shutdown losses count only where the plant must be shut down solely for the measure. Savings the measure brings are offset against its cost. The duty holder’s ability to pay is not a legitimate factor.
HSE’s CBA checklist sets out what it expects to see included and challenged. The table summarises it.
Table 2. What belongs in the sacrifice side of an ALARP comparison
| Item | Treatment |
|---|---|
| Installation, operation, training and additional maintenance | Counts |
| Ongoing production losses caused by the measure (slower operation, extra maintenance downtime) | Counts |
| Shutdown losses where the plant is shut down solely to implement the measure | Counts, but the duty holder should show that scheduling the work into a planned outage would not change the conclusion |
| Lost production | Only the production lost during the delay; where production is deferred rather than lost, only the cost of deferral |
| Savings from the measure (reduced operating cost, avoided damage and reinstatement) | Offset against cost; not counted as a safety benefit |
| Costs borne by other parties | Excluded |
| Costs beyond what is necessary and sufficient for the safety purpose | Excluded |
| Costs of wider commercial changes bundled with the measure | Excluded from the ALARP comparison; record separately |
| The duty holder’s size, financial position or project viability | Not a legitimate factor |
On the benefit side, HSE expects all risk reduction to be counted: prevented fatalities, injuries and ill health to workers and the public, environmental damage where relevant under COMAH, and avoided emergency response and evacuation. A measure aimed at one scenario that also reduces others should be credited with all of them.
How large does the disproportion need to be?
There is no fixed figure. HSE has not published an algorithm for the disproportion factor; it must be argued for the circumstances, and it increases with the size of the risk. For a major accident hazard, HSE’s own screening example treats a factor above 10 as unlikely. Conclusions close to the threshold need sensitivity analysis before they can support rejecting a measure.
HSE’s CBA checklist includes a coarse screening example for a chemical plant explosion with a frequency of 1 in 100,000 per year over a 25-year plant life. It shows how small the monetised benefit of a rare event can look, and why the disproportion factor and the risk basis matter more than the arithmetic.
Table 3. HSE coarse screening example (HSE values at 2003 prices, no discounting or inflation)
| Harm prevented | Number | Value per case | Benefit over 25 years at 1 × 10⁻⁵ per year |
|---|---|---|---|
| Fatalities | 20 | £1,336,800 | £6,684 |
| Permanently incapacitating injuries | 40 | £207,200 | £2,072 |
| Serious injuries | 100 | £20,500 | £512 |
| Slight injuries | 200 | £300 | £15 |
| Total benefit | £9,283 |
Applying a disproportion factor of 10, HSE concludes it might be reasonably practicable to spend in the region of £93,000 to eliminate the risk. The figures are illustrative: they use 2003 values, and a real assessment should use current appraisal values and justify them.
Three points from the same guidance decide whether a CBA is defensible.
- Sensitivity. Inputs to major accident CBAs can carry uncertainty ranges of a factor of three or more. Unless the extreme values have been used, a result that exceeds the disproportion factor by less than that range is not a compelling reason to reject a measure.
- Discounting. Discounting is permitted, but HSE’s checklist applies a lower rate to future safety benefits than to future costs, and a measure should not be rejected because of a discounting choice in a finely balanced case.
- Societal risk. HSE’s principles reflect a greater aversion to a single event harming many people than to the same number harmed separately, which supports a higher factor where multiple fatalities are credible.
Worked example: a blocked-outlet overpressure scenario
This example is illustrative and is not drawn from a specific client project.
A HAZOP identifies that a blocked outlet could overpressure process equipment beyond its design pressure. The team records the scenario, the initiating causes and the safeguards claimed, then uses LOPA to test the initiating frequency, the credit taken for each independent protection layer and the residual risk against the site’s criteria. A relief device is credited only if it is confirmed as sized for this case and its disposal route is acceptable.
The gap identified by the LOPA leads to four candidate options.
Table 4. Options for the overpressure scenario
| Option | Type | Key considerations |
|---|---|---|
| Rate the equipment for the maximum pressure the system can generate, or change the source so it cannot exceed design pressure | Inherent | Removes the scenario; may require equipment replacement at a planned shutdown |
| Pressure relief sized for the blocked-outlet case | Engineered, passive | Relief sizing and disposal route, inspection and testing, and any new hazard created by the release |
| Independent high-pressure trip implemented as a safety instrumented function to IEC 61511 | Engineered, active | Required safety integrity level, independence from the basic process control system, final element, proof testing and spurious trip consequences |
| Revised operating limits and procedures | Procedural | Limited risk reduction credit; dependent on human reliability |
Each option is assessed for the risk reduction it delivers, its independence and reliability, any new hazards, operability, maintainability, shutdown needs, programme and cost. The engineering evidence differs by option. For the trip, the review covers sensor reliability, voting, proof testing, the final element and integration with the control and shutdown systems. For an equipment or piping change, it covers pressure drop, equipment rating, access, maintenance and the shutdown needed for construction. If the team selects the trip rather than the inherent change, the record has to explain why the inherent option was not reasonably practicable, not simply that the trip was cheaper.
What delivered studies show
Two of IDEA’s published projects illustrate the stages where ALARP decisions are most often won or lost.
The first is the quality of the risk basis. At a whisky distillery where formal studies had not previously been completed, IDEA delivered a combined HAZOP, LOPA and HEART assessment. Conservative generic human error assumptions in the LOPA were driving high calculated safety integrity level (SIL) requirements. A HEART (human error assessment and reduction technique) study derived task-specific human reliability values, which reduced unrealistic SIL requirements and supported prioritised recommendations towards an ALARP risk position. The lesson is not that risk should be argued down. It is that an ALARP judgement is only as sound as the risk estimate it rests on, in either direction.
The second is defining the requirement before comparing options. For a whisky blending facility, IDEA established the operational routing requirement with operators through route matrix workshops before evaluating flow plates, valve matrices and hybrid arrangements against safety, human factors, operability, maintainability, capital cost and operating cost. That project was framed as risk reduction optioneering rather than a formal ALARP case, but the discipline is the same one stage 3 and stage 6 require: a defined basis, a genuine range of options and a stated reason for the choice.
Both projects are in the distilled spirits sector, where large flammable inventories, live operations and ageing assets make proportionate decisions on retrofit measures a recurring question.
A third study shows the comparison itself. At a Scotch malt whisky distillery, IDEA assessed whether emergency fire relief venting should be retrofitted to 16 spirit tanks across five areas of the site. LOPA established the escalation frequency in each area, and a cost benefit analysis compared the cost of retrofit vents with the risk reduction they would deliver. The proportion factors ranged from 12.8 to 43.8, above the factor of 10 applied for the most severe events, so the vents were grossly disproportionate in every area. The study then calculated the spend each area could justify for any measure giving a tenfold risk reduction, between about £2,200 and £29,100. It recommended flammable gas detection with executive shutdown action as a more effective safeguard, because it acts before a fire develops.
What a defensible ALARP record contains, and how IDEA can help
A record that will stand up to scrutiny captures:
- the scenario, scope, boundaries and assumptions;
- the current safeguards and the risk basis, including how uncertainty was treated;
- the relevant good practice considered and how it was applied;
- the options identified, their expected risk reduction and their feasibility;
- the sacrifice for each option, the disproportion factor and the sensitivity analysis where a CBA was used;
- the selected measures and the reasons each credible alternative was rejected;
- the residual risk, the actions, owners and dates, and the triggers for review;
- approval by the person with authority over, and ownership of, the residual risk.
For an initial discussion, it helps to have the scenario definition, HAZOP and LOPA records, current safeguards, candidate options and technical constraints, order-of-magnitude costs, and the decision authority and deadline.
IDEA’s process safety team, based in Glasgow, supports duty holders through each stage: scenario definition through HAZOP, HAZID and LOPA studies, multidisciplinary optioneering, cost benefit analysis, ALARP demonstration within COMAH safety reports, and engineering of the selected measures. If you have HAZOP or LOPA actions awaiting a decision, our ALARP demonstration and cost benefit analysis service sets out how we work, or you can contact our process safety team to discuss the risk basis and options with your engineers.
Frequently Asked Questions
In substance, yes. HSE considers that duties to reduce risk “as low as reasonably practicable” and duties to ensure safety “so far as is reasonably practicable” call for the same set of tests. The terms are not interchangeable in legal proceedings, which must use the wording of the relevant legislation.
No, unless the alternative measures are shown unequivocally to be at least as effective. HSE’s CBA checklist also states that a CBA on its own does not constitute an ALARP case. It cannot be used to argue against statutory duties, and it cannot justify an intolerable risk.
No. HSE has not published an algorithm for the factor. It must be argued for the circumstances, and the greater the risk, the larger the disproportion can be before it counts as gross. In HSE’s screening example for a major accident explosion, a factor above 10 is described as unlikely, and conclusions close to the threshold need sensitivity analysis.
Installation, operation, maintenance and training costs count, along with production lost because of the measure. Shutdown losses count only where the plant is shut down solely to implement it. Savings the measure brings are offset against its cost. HSE does not take a duty holder’s size or financial position into account, so ability to pay is not a factor.
Not necessarily. HSE accepts that reducing risk ALARP on existing plant can leave a higher residual risk than on a comparable new plant. Retrofitting can be less practicable, costs more and carries installation risks of its own. Each measure is still judged on the site-specific risk and cost, and partial upgrades or alternative measures may be required where a full upgrade would be grossly disproportionate.
CONTACT US
How IDEA can support ALARP assessment
IDEA can facilitate scenario definition, LOPA, option generation, multidisciplinary feasibility review, Cost Benefit Analysis, ALARP documentation and engineering development of the selected measures.