Aquaculture System EC&I Design and Installation Cost Estimate

An aquaculture technology company asked IDEA to produce a cost estimate for the electrical, control and instrumentation (EC&I) design and installation scope associated with a recently installed Recirculated Aquaculture System (RAS). The purpose was to create a clear benchmark of design deliverables and installation costs, and to test whether alternative design and installation routes could deliver savings for future RAS projects in Scotland.

At a glance

  • Sector: Food & Drink Manufacturing
  • Scope: EC&I design and installation cost benchmark for a completed RAS project
  • Disciplines: Electrical, control and instrumentation design and cost estimating
  • Outcome: A clear, auditable cost baseline to inform future RAS delivery decision

Client Overview

The client is an aquaculture technology company that had recently installed a Recirculated Aquaculture System (RAS) and wanted a clear cost benchmark for the EC&I design and installation scope.

The purpose was to test whether alternative design and installation routes could deliver savings for future RAS projects in Scotland.

The challenge: a transparent, protected cost baseline

The challenge was to build a transparent EC&I cost baseline from existing documentation alone, capturing the full scope while protecting the client's project information under NDA.

  • Requiring a transparent cost baseline for EC&I design and installation, based on a completed project.
  • Capturing the full EC&I scope, equipment, cabling, containment, installation and termination, via a competent local contractor, while protecting project information under NDA.
  • Completing the work using existing documentation, with no site survey included in the estimate scope.

IDEA's role

IDEA reviewed existing documentation and built a structured, contractor-priced cost baseline for the EC&I scope.

  • Documentation review and RFI to close gaps in the electrical design and installation documentation.
  • Defined the complete EC&I deliverable set and built an associated design cost estimate.
  • Produced a Scope of Work pack for a local EC&I contractor to price equipment, containment, cabling, installation and termination.
  • Held project meetings and a cost review workshop to reconcile scope and confirm assumptions.

What we delivered

The delivered package gave the client a defined deliverable set and a contractor-priced cost estimate for future reference.

  • Review of EC&I documentation and issued RFI.
  • Defined list of EC&I design deliverables, with associated cost to deliver in future.
  • Scope of Work pack issued to an EC&I contractor for pricing of equipment, labour and subsistence.
  • Detailed contractor cost estimate for EC&I design and installation.
  • Workshop session to review and align on the design and installation cost basis.

Results and outcome

The estimate gave the client a clear, auditable cost baseline and supported informed comparison between delivery routes for future projects.

  • Provided a clear, auditable cost baseline for EC&I design and installation, reducing uncertainty when planning future RAS deployments.
  • Enabled like-for-like comparison between delivery routes, supporting informed decisions on potential cost savings.
  • Reduced procurement and scope-gap risk by packaging requirements into a structured Scope of Work.
  • Protected client information through NDA controls, supporting open commercial evaluation without compromising confidentiality.

Why IDEA for EC&I cost benchmarking

IDEA builds transparent, contractor-priced cost baselines that support confident decision-making on future project delivery routes.

  • Structured EC&I deliverable definition from existing documentation.
  • Contractor-priced Scope of Work packages for transparent benchmarking.
  • NDA-aware working to protect client confidentiality.
  • Experience supporting aquaculture and process facility cost planning.

Frequently Asked Questions

An EC&I cost baseline for a RAS project typically covers equipment, cabling, containment, installation and termination costs, benchmarked against a completed project's documentation and priced by a competent contractor.

Where the objective is to benchmark cost from a completed project, using existing documentation avoids the time and cost of a new site survey while still producing a representative baseline for comparison purposes.

Confidentiality is protected through NDA controls with both the client and the pricing contractor, allowing commercial evaluation to proceed without exposing sensitive project information beyond what is necessary.

A Scope of Work pack defines the equipment, labour and installation requirements clearly enough for a contractor to provide a structured, comparable price, reducing the risk of scope gaps or misunderstandings.

A cost baseline allows a business to compare alternative design and installation routes on a like-for-like basis, supporting more informed decisions about how to deliver similar projects in future.

CONTACT US

Need a transparent cost baseline for a completed or planned project?

IDEA builds contractor-priced EC&I cost baselines to support confident decisions on future project delivery routes.

Subscribe

* indicates required